Bond at Work

John Q. Adams Elementary School
Renovations

  • Construction Started

    1
  • Complete

    2
Current Status

Project Highlights


  • School Modernization
    • Paint common interior areas (excluding classrooms) and paint exterior areas as applicable
  • Building Envelope
    • Exit doors replacement as assessed including frame and associated hardware
  • Mechanical, Electrical and Plumbing
    • Heating, Ventilating, and Air Conditioning (HVAC) distribution system refurbishment as determined by the A/E Team
    • Pump replacements as assessed by Dallas ISD assessment teams
    • Variable Air Volume (VAV)  / Single zone air handling unit replacement as assessed
    • Direct Digital Controls (DDC) replacement / addition
    • Lights replacement in areas prioritized by the assessment teams
    • Stage lights replacement as assessed by Dallas ISD assessment teams
    • Grease trap upgrades
  • Restroom Refurbishments
    • Scope as identified by assessment teams
  • Sitework / Grounds
    • Parking lot paving and striping as assessed
    • Playground equipment and fall zone replacement
    • Dumpster pad and fencing around dumpsters as required for code compliance
  • Kitchen and Dining Refurbishments
    • Dining / Kitchen infrastructure refurbishments

 

Project Information

Location:

8239 Lake June Road
Dallas, TX 75217
View Map

Trustee:

Nancy Bingham, District 4

Project Status:

Complete

Project Manager:

Jacobs Engineering Inc.

Architect:

Boynton Williams & Assoc.

Contractor: