Bond at Work

Nathaniel Hawthorne Elementary School
Renovations

  • Construction Started

    1
  • Complete

    2
Current Status

Project Highlights


  • School Modernization
    • Paint common interior areas (excluding classrooms) and paint exterior areas as applicable
  • Building Envelope
    • Exit doors replacement as assessed including frame and associated hardware
  • Mechanical, Electrical and Plumbing
    • Chiller replacements as assessed, including Direct Digital Controls (DDC)
    • Lights replacement in areas prioritized by the assessment teams
    • Stage lights replacement as assessed by Dallas ISD assessment teams
    • Grease trap upgrades
  • Restroom Refurbishments
    • Scope as identified by the assessment teams
  • Sitework / Grounds
    • Parking lot paving and striping as assessed
    • Playground equipment and fall zone replacement
    • Dumpster pad and fencing around dumpsters as required for code compliance

 

Project Information

Location:

7800 Umphress Road
Dallas, TX 75217
View Map

Trustee:

Nancy Bingham, District 4

Project Status:

Complete

Project Manager:

Jacobs Engineering Inc.

Architect:

Boynton Williams & Assoc.

Contractor: